These USAF engineers are at the leading edge of one of the largest military construction efforts since Vietnam.
The RED HORSE Way
By Peter Grier
|
|
At right, members from the 819th/219th Expeditionary
RED HORSE fit together building arches at al Udeid
AB, Qatar, on New Year’s Eve 2002.
|
The Air Force’s elite corps of rapid deployment
civil engineers is working miracles in Afghanistan,
Qatar, Kyrgyzstan, and other austere locations that
are the scenes of Operation Enduring Freedom and other
US actions in the region.
They are the Rapid Engineer Deployable Heavy Operational
Repair Squadron Engineer, better known as RED HORSE,
units.
These outfits have undertaken huge tasks ranging from
the largest aircraft parking ramp project in history
to renovation of living quarters at former Taliban bases
in Afghanistan. They’ve repaired runways in blackout
conditions and, at one forward base, laid enough gravel
to build a road that would stretch from the Pentagon
to Langley Air Force Base in the Tidewater area of southeastern
Virginia.
With an estimated $100 million worth of projects under
way at the end of 2002, RED HORSE squadrons are the
leading edge of one of the largest military construction
programs since Vietnam. “These are awesome accomplishments,”
said Col. Fred Wieners, director of Task Force Enduring
Look, an Air Force effort to document lessons learned
in the war against terrorism. “What other country
could go halfway around the world and do that?”
Consider the scale of the ramp project—the biggest
single job a RED HORSE unit has ever undertaken.
In this venture, Air Force engineers from the 820th
and 823rd RED HORSE units spent five months transforming
a scrub-and-sand Gulf desert site into a paved airfield
the size of about 20 combined football fields.
Members of the 820th, who deployed from Nellis AFB,
Nev., and 823rd, from Hurlburt Field, Fla., and an assortment
of other Air Force engineering personnel worked around
the clock to finish the project early. The ramp—at
al Udeid in Qatar—is some 44,000 square feet larger
than the previous record holder’s ramp, which was
built by the 554th RED HORSE in 1967 at Phan Rang Air
Base in what was then South Vietnam.
Record Time
“They built this thing [at al Udeid] in record
time,” noted Maj. Gen. Earnest O. Robbins II, the
Air Force civil engineer, at the Pentagon. “Outside
contractors estimated it would take months.”
The project called for pouring more than 1,000 cubic
yards of concrete every 24 hours. A typical work day
saw movement of up to 350 trucks on and off the site.
“They actually had to build up this entire area
by about three and a half feet,” said Robbins.
“It was a rather incredible construction project.”
Besides the ramp, RED HORSE members built at the same
base some 124,000 square feet of covered maintenance
space and a new fire station, warehouse, four hangars,
and a squadron operations facility. They laid 10,000
feet of conduit and built water-handling facilities
for both fire-fighting and personnel consumption.
RED HORSE units are the civil engineering SWAT teams
of the Air Force. They are 404-person units whose mission
is to move quickly to support special operations or
contingency deployments worldwide.
They are trained to operate in high-threat environments
with little or no contractor support, and they are so
self-contained that they can deploy with their own weapons,
equipment, and even food service and medical support
if need be.
Their specialty is what Air Force officials have called
“horizontal capability”—runway and ramp
construction, maintenance, and repair. However, they
are meant to be extraordinarily flexible, and they can
do virtually all civil engineering tasks, from damage
assessment to the erection of buildings on previously
bare bases.
Some units possess special capabilities. These range
from well-drilling to explosive demolition and quarry
operations. In Fiscal 2003, plans even call for the
addition of airdrop capability to some squadrons, allowing
them to deliver light equipment and personnel by airdrop
or other air transport means.
Current doctrine organizes the squadrons into four
deployment echelons. The first has 16 persons who are
capable of assessment and site preparation and ready
to move within 16 hours of notification. The second—with
148 people—can be ready to deploy within 96 hours
and adds heavy bomb damage repair and light base development
to the capabilities mix. The third element—with
120 personnel—moves six days after notification,
and the fourth—with another 120 personnel—moves
two days later and brings a RED HORSE unit to full strength.
Four of the Air Force’s seven RED HORSE squadrons
are active duty. The remainder are provided by the Air
National Guard and Air Force Reserve Command. The latter
are split units, with the two halves being located at
different bases and serving under different commanders.
For example, the 200th RED HORSE, Port Clinton, Ohio,
combines with the 201st RED HORSE, Fort Indiantown Gap,
Pa., to form a full unit.
Vietnam Roots
The roots of RED HORSE are in the Vietnam era, when
then–Secretary of Defense Robert S. McNamara asked
the Air Force to develop an in-house combat construction
capability similar to that of the Navy’s Seabees.
RED HORSE was the result.
Since that time, the squadrons—whose emblem is
a snorting, armed red horse driving a bulldozer—have
played a key role in Air Force contingency operations.
In the 1991 Gulf War, for instance, a composite RED
HORSE force drawn from a number of squadrons completed
more than 25 construction projects at 12 different sites
in the Gulf region.
Much of the work was in Saudi Arabia. At al Kharj,
just south of Riyadh, RED HORSE personnel supervised
the construction in a matter of weeks of an air base
capable of handling five fighter squadrons. They built
berms to protect Patriot missile sites for the Army.
At the end of the war, per order of the Gulf War air
boss, then–Lt. Gen. Charles A. Horner, they essentially
destroyed two air bases in southern Iraq by cutting
runways and blowing up hardened aircraft shelters.
In the war on terrorism, the RED HORSE units have had
a chance to really stretch their legs. The work the
units have undertaken for Enduring Freedom has been
perhaps their biggest challenge ever.
“Certainly in terms of magnitude, the size of
the projects, their duration, these are the most sustained
RED HORSE operations” since the 1960s, said Robbins.
Since the United States on Oct. 7, 2001, launched its
attack on Taliban forces in Afghanistan, RED HORSE units
have gone to a total of 26 sites in the region. At 12
of these bases, the units did actual construction. At
14 they did site surveys or other assessment work.
Some 1,400 RED HORSE personnel, from five different
squadrons, have cycled through the Enduring Freedom
theater of operations. Specialties most in demand have
been those associated with runway work, which includes
everything from concrete mixing to airfield lighting
installers.
RED HORSE work for Operation Enduring Freedom can be
essentially divided into two main categories, according
to Air Force officials.
The first is the construction of new air capacity in
expectation of future requirements. The construction
at al Udeid is a good example of this. Air Force personnel
have essentially created a giant new forward operating
base in months—one that is the equal of facilities
in Saudi Arabia.
|
|
Members of the 823rd RED HORSE level an area
of the desert in preparation for a new aircraft
parking ramp. The region’s harsh conditions
make the engineering unit’s job a particular
challenge.
|
Bomb and Build
The second is repair work on existing but decrepit
facilities. A perfect example of this is Bagram, the
main air base in Afghanistan. Built by the Soviets during
their ill-fated Afghan occupation of the 1980s, Bagram
suffered considerable damage during the brief allied
campaign against the Taliban. RED HORSE was then charged
with going in and rebuilding what 500-pound Air Force
bombs had torn asunder.
US runways typically feature smooth and continuous
concrete surfaces. The Soviet style, however, was to
build in concrete slabs. In theory, this makes construction
easier. In practice, upkeep becomes a nightmare.
“You have all these joints running laterally and
horizontally,” said Robbins. “It is a constant
maintenance problem to try to keep the airfield smooth.”
Each 11-by-13-foot concrete slab takes an hour or more
to repair. RED HORSE teams—in conjunction with
other USAF civil engineering units—repaired or
replaced more than 2,500 of them.
“Allied forces had done a really good job of destroying
that airfield,” said the top Air Force civil engineer.
At one point during this process, US commanders at
Bagram decided the security situation was such that
some of the repairs should take place at night, with
the RED HORSE members using night vision equipment.
Partly for this reason—and partly because it was
a good training opportunity—the 200th/201st RED
HORSE went out and successfully poured concrete in complete
darkness, using only night vision equipment.
“That’s the first time we’ve ever done
that, to my knowledge,” said Robbins.
The difficulty of this operation was compounded by
the fact that the crew was using a deployable pavement
repair system. This mobile concrete machine is designed
for rapid repairs and thus produces only limited quantities
of concrete quickly. It is a high-performance machine
that is sensitive to such variables as the size of stone
and quality of sand.
Yet RED HORSE used the deployable system for half their
Bagram repairs—running it continuously for three
months. In between the slab repairs, the units found
time to reconstruct the base Air Force Village, build
new showers and laundry facilities, put up several hundred
feet of security walls, rewire the air traffic control
tower, and pave a basketball court.
Installations from Qatar to Kyrgyzstan have received
a similar, full-court-press RED HORSE treatment—all
in a region where everything from the climate to the
scarcity of local resources makes construction difficult.
“It has been a test unlike any that we have ever
experienced,” said Robbins.
Hard Rock
In Qatar and other Gulf–side locations, the temperature
can hit 120 degrees and humidity about 90 percent. In
those conditions, Air Force construction personnel can
only work about 30 minutes at a time before they have
to take a break, and concrete does not pour well. The
ubiquitous sand fouls work and machinery alike.
“Plus,” noted Robbins, “we learned that
some of the hardest rock in the world exists over there.”
In the buildup to the 1991 Gulf War, contractor support
was plentiful, as the US was operating with Arab allies
and staging from some of the wealthiest nations in the
Middle East. But Afghanistan and Pakistan are not Saudi
Arabia or even Qatar. Much of the challenge to RED HORSE
in recent months has come from operating virtually alone.
“In one instance [at an undisclosed location]
we found one guy with one dump truck,” recalled
Robbins. “He was the sum total of our contractor
capability.”
This person performed valiantly in delivering aggregate,
added Robbins, and became highly popular with the RED
HORSE leadership. Overall, however, this problem represents
one of the primary civil engineer lessons learned from
the Enduring Freedom operation.
“Assumptions regarding host nation support are
not always valid,” said Robbins.
Elsewhere, RED HORSE made extensive use of the Air
Force Contract Augmentation Program. AFCAP allowed Air
Force planners to go to contractors and simply say they
needed a particular piece of equipment at a particular
place and time. It was up to the private sector to find
the equipment and ship it to the port nearest the location
in question.
One reason service logisticians like this approach
is that it often results in new, or nearly so, heavy
machinery for Air Force use. Most service equivalents
are old and in need of replacement.
“This gives us a way ahead,” said Robbins.
“More and more we are looking at augmenting Air
Force personnel with leased private sector equipment.”
|
|
TSgt. John Deyo, 819th/219th RED HORSE, works
on the construction of a new transportation building.
Members worked 12-hour days, six days a week,
to prepare forward locations for operations in
support of Enduring Freedom.
|
There Were Others
The intensive OEF experience has also taught the Air
Force that its reserve RED HORSE units are as capable
as their active duty equivalents. And it has reconfirmed
the fact that RED HORSE squadrons are only one part
of the service’s civil engineering equation.
RED HORSE represents an “incredible capability,”
said Robbins. It kicks down the door and readies locations
for all that follow. Other services, however, have contributed
to this effort in Afghanistan—notably the Seabees.
And the majority of Air Force civil engineering personnel
are not RED HORSE but members of Prime BEEF combat support
units.
Prime BEEF, for Base Engineer Emergency Forces, has
deployed to Afghanistan and other Middle East sites
in the wake of RED HORSE to pick up maintenance and
continued construction at key bases.
At Bagram, for instance, Air Force civil engineers
drawn from four different units helped RED HORSE repair
concrete slabs and installed a lighting system that
allowed the field to go from a covert no-visible-light
landing status to overt landings.
“Many are deployed for a long time,” said
Robbins. “They are carrying a huge part of this
load. It’s a total team effort.”
And that effort is invaluable to the war on terrorism
as a whole. Task Force Enduring Look—the war on
terror lessons-learned project—has listed the ability
to provide base operations support early as key to the
allied success.
“There is a tendency to want to put iron down
first—those weapons we can use to do harm to the
enemy,” Wieners told an Air Force News interviewer
earlier last year. “But it is important to find
that right balance to ensure your people can survive,
so that they can operate. It is a difficult challenge,
especially at austere basing, as we saw in Central Asia.”