STATEMENT OF SUBJECT MATTER AND APPELLATE JURISDICTION
This Court has jurisdiction pursuant to 49 U.S.C. 46110(a).
National Parks and Conservation Ass’n v. FAA, 998 F.2d 1523, 1528
(10th Cir. 1993).
On December 31, 2001, respondent Federal Aviation Administration
(“FAA”) issued a Record of Decision (“ROD”) approving the expansion of
the Piedmont Triad International Airport (“PTIA”) in Greensboro, North
Carolina. The ROD constitutes
“the final agency determinations and approvals” of the FAA.
ROD, p. 1.*[1]
On January 17, 2002, less than 60 days after the FAA issued the ROD,
petitioners Alliance for Legal Action and seven individual petitioners
(“petitioners”) petitioned this Court to review the ROD.
Petitioner Alliance for Legal Action is a non-profit corporation, which
has over 900 contributors. Many
of these contributors and individual petitioners live within one mile of the
proposed new runway and will be seriously affected by the noise resulting from
the proposed operations. Ex. 28,[2] paras. 2, 3, 8.*
Some contributors have had their land condemned.
Id., para. 2.*
STATEMENT
OF THE ISSUES
1. Whether
the FAA violated the National Environmental Policy Act, 42 U.S.C. 4321, et
seq. (“NEPA”), by relying on inaccurate data and incorrect assumptions
in setting forth the need for the project.
2. Whether
the FAA violated NEPA by defining the purpose of the project too narrowly.
3. Whether
the FAA violated NEPA and the Airport and Airways Improvement Act, 49 U.S.C.
47101, et seq. (“AAIA”), by
failing to analyze any off-site alternative.
4. Whether
the FAA violated NEPA and the AAIA by rejecting any on-site alternative that
involved expanding the current, perpendicular runway configuration.
5. Whether
the FAA violated NEPA and the AAIA by failing to disclose adequately the noise
impacts.
6. Whether
the FAA violated NEPA and the AAIA by failing to disclose the toxic air
emissions.
7. Whether
the FAA violated NEPA and the AAIA by failing to analyze the induced-growth
effects.
STATEMENT
OF THE CASE
On April 5, 2000, the FAA issued a draft environmental impact statement
(“EIS”). See
65 Fed. Reg. 17,938. Petitioners
submitted comments on that draft. R.
318-319.[3] On
November 16, 2001, the FAA issued the final EIS (“FEIS”).
See 66 Fed. Reg. 57,716.
Petitioners again submitted comments.
R. 338-339. On December
31, 2001, the FAA issued the ROD. See 67 Fed. Reg.
3,777.
On January 17, 2002, petitioners filed their Petition for Review.
On January 25, 2002, the Piedmont Triad Airport Authority (“Airport
Authority”) filed a motion to intervene.
On January 29, 2002, this Court granted that motion.
STATEMENT
OF FACTS
PTIA currently encompasses approximately 3,100 acres and has two
runways. FEIS, p. 1-8.*[4]
Its primary runway, 5/23, is 10,001 feet long.
Ibid. Its second
runway, 14/32, is perpendicular to runway 5/23 and is 6,380 feet long.[5]
Ibid.
This project involves the construction of a new, third runway, 5L/23R,
and a cargo sorting/distribution facility.
ROD, p. 1.* The runway
will be 9,000 feet long. FEIS, p.
1-5.* It will be to the north of
and parallel to the existing 10,001-foot runway.
ROD, p. 1.* See
FEIS, figure S-1.* The sorting
facility will be located at the northeastern end of PTIA and in the middle of
the parallel runways. FEIS, pp.
1-2, 2-15.* The facility will
cover 300 acres of land. Id., pp. 1-6, 2-15.*
FedEx currently has 26 daily operations at PTIA.[6]
FEIS, p. 1-9.* The proposed project has two phases: Phase 1 (present-2005) and Phase 2 (2006-2019).
Id., p. 2-6.*
In 2005, FedEx will expand to 48 daily operations at PTIA.
Id., table 1.3-1.*
In 2009, FedEx will expand to 126 daily operations.
Ibid.
FedEx will operate its hub at PTIA between 10:00 PM and 7:00 AM.
FEIS, p. 5-10.* During
Phase 1, aircraft will begin arriving at 10:00 PM and finish by 1:00 AM. Ibid.
The Phase 1 departures will begin at 4:00 AM and end at 6:00 AM.
Ibid.*
Phase 2 operations are similar except that the arrivals occur from
10:00 PM to 2:00 AM and the departures begin at 4:00 AM and end at 7:00 AM.
Ibid.
Thus, once fully operational, all of the planes will land within 4
hours (10:00 PM to 2:00 AM) and take off within 3 hours (4:00 AM to 7:00 AM).
The sole purpose of the airport expansion is to allow FedEx to
establish a Mid-Atlantic cargo hub at PTIA since, at least through 2019, no
other air carrier will use the new runway.
FEIS, p. 1-2, table 5.1.2-7.*
PTIA services mainly Greensboro, High Point, and Winston-Salem.
These are the largest cities in a 12-county triangular region. FEIS, p. 4-2.* Within
5 miles of PTIA, there are 17,215 single-family homes, 2,684 multi-family
homes, and 13 churches. Id., table 4.2.1-5, p. 4-3.*
The nighttime operations from this project will create new noise
impacts in the surrounding communities. Noise
can cause hearing damage, contribute to heart disease, cause stress and
hypertension, affect the quantity and quality of sleep, interfere with
conversation and social interaction, hinder the development of language skills
in children, interfere with a person’s ability to work, and make a person
more irritable, depressed and aggressive.
Ex. 29, pp. 13-14.*
The project will result in an increase in emissions of nitrogen oxides
and volatile organic compounds. ROD,
p. 56.* These compounds are “two of the primary precursors to the
formation of ozone.” Ibid.
Ozone is an odorless, colorless gas.
American Trucking Ass'ns, Inc. v.
EPA, 283 F.3d 355, 359 (D.C.
Cir. 2002). “Significant health
effects associated with ozone pollution include coughing; throat irritation;
aggravation of existing conditions like asthma, bronchitis, heart disease, and
emphysema; and lung tissue damage” (citations omitted).
Ibid.
The FAA
estimates that the project will cost $228,000,000.
FEIS, table S-2.* The FAA will provide $108,000,000 in federal taxpayer dollars
towards those costs. Amy Joyner, FAA
Approves Money to Build 3rd PTI Runway, Greensboro News & Record,
March 22, 2002, p. A1.
PTIA opened to commercial traffic in 1928.
FEIS, p. 1-7.* The
planning of the proposed runway dates back to 1968.
See Ex. 6.* However,
the runway was planned to be only 5,000 feet long.
Ibid.
Five years later, the 1973 Airport Master Study Plan stated that a new
runway would be required sometime between 1987 and 1990 and that the
“planned ultimate length of this runway should be 6,500 feet.”
Ex. 7, p. 4.* As of 1990,
the level of demand at PTIA apparently did not require the new runway since no
proposal for it was ever made.
In 1973, the Guilford County Board of Commissioners approved the
development of the Cardinal Community, a Master Planned Urban Development,
located to the northeast of PTIA. R.
23, p. 1; Ex. 28, para. 5.* The
Cardinal is located less than one half of a mile from the northeastern end of
the proposed 9,000-foot runway. Id., para. 8.*
Since 1973, the Cardinal has grown rapidly and now has approximately
800 to 1,000 homes and 2,500 residents. R.
23, p. 1; Ex. 28, para. 5.*
In 1990, PTIA’s Master Plan Update depicted plans for a new,
7,000-foot parallel runway. Ex.
8, p. IX-2.* However, the
document stated that it would be used only by “small single and twin-engine
propeller aircraft conducting routine take-offs, landings, and touch-and-go’s;
a nominal percentage (10%) of all military sorties; and approximately 10% of
the air carrier operations.” Id.,
p. VII-2.* By 1990, the
communities at the northeastern and southwestern ends of the planned runway
had developed considerably. Ex.
28, para. 8.*
In 1994, the Airport Authority first changed its airport layout plan to
reflect a proposal to build a new, 10,000-foot parallel runway, allowing
larger and heavier aircraft to use it than the ones identified in the 1990
Plan Update. See Ex. 9; Ex. 28,
para. 7.* This proposal first
arose around 1992 in connection with the PTIA’s efforts to compete for the
Global Transpark, a large cargo facility that the State of North Carolina was
sponsoring. Ibid. In May 1992, the
State selected the Kinston Regional JetPort as the site for the Global
Transpark. Ex. 22, p. 3.*
As a result, PTIA’s proposal for a new runway never materialized.
In November 1997, FedEx notified several airports in North Carolina and
South Carolina, including PTIA, that it was thinking about developing a
Mid-Atlantic cargo hub and invited them to submit proposals.
See, e.g., Ex. 17.*
PTIA, the Global Transpark, Raleigh-Durham International Airport,
Charlotte International Airport, Greenville-Spartanburg International Airport,
and Columbia International Airport all did so.
FEIS, p. 2-5.* On April 13, 1998, FedEx selected PTIA. Ex. 36.*
On May 10, 1999, in preparing its draft EIS, the FAA inquired as to why
FedEx selected PTIA. R. 144, p. 3.* FedEx
responded that its “selection analysis is confidential and proprietary to
FedEx * * *.” R. 145, p. 2.*
FedEx provided the FAA with a list of criteria and stated only that it
had rated PTIA the best site. Ibid.
See FEIS, p. 2-5.*
In 1998, the Airport Authority sought the FAA’s approval to construct
the new runway and the sorting facility.
On December 31, 2001, the FAA approved the request.
SUMMARY OF ARGUMENT
1. The FAA
concluded that this project is needed based on the assumptions that FedEx
requires at least 9,000 feet of runway, there must be two runways of that
length, the runways must be parallel in order to permit head-to-head
operations, and the sorting facility must be in the middle.
These assumptions are contradicted by undisputed evidence.
Indeed, most of FedEx’s other cargo hubs do not contain such
operating conditions. Thus, the
determination of the need for this project was based on inaccurate data and
erroneous assumptions in violation of NEPA.
2. The FAA
defined the purpose of this project as developing parallel, 9,000-foot runways
with a sorting facility in the middle. This
definition was too narrow since FedEx could have efficiently located its cargo
hub at an airport without these characteristics.
As a result, the FAA eliminated reasonable alternatives from detailed
consideration in violation of NEPA.
3. The
heart of an EIS is its analysis of reasonable alternatives.
The FAA’s alternatives analysis did not comply with NEPA and the AAIA
because it failed to consider in detail a single off-site alternative to this
project. Some, if not all, of the
very airports that competed with PTIA to serve as FedEx’s Mid-Atlantic hub
are reasonable alternatives. However,
they were all eliminated without analysis because FedEx had determined that
its hub should be located at PTIA and the other sites were not PTIA.
In addition, FedEx refused to provide any information to the FAA as to
why it had rejected these other airports.
4. The
FAA’s alternatives analysis did not comply with NEPA and the AAIA because it
failed to consider any on-site alternative that would expand the current,
perpendicular configuration as opposed to developing a new, parallel runway.
The FAA dismissed any such alternative because it would not provide for
parallel runways with a sorting facility between them.
However, perpendicular runways could accommodate FedEx’s operations
and would require less federal taxpayer monies, condemn less private property,
and create less environmental harm.
5. The FAA
failed to disclose adequately the noise impacts. The FAA assumed that 95 percent of all of FedEx’s
operations would occur to and from the southwest.
This assumption was critical because it was the basis for the FAA
concluding that there would be hardly any noise impacts on one end of the new
runway where there are approximately 1,000 residential homes and 2,500 people.
There is no justification for this assumption since it is contrary to
the ordinary operation of airports and FedEx has made no commitment to operate
in this manner.
The FAA’s noise model underestimates the impacts from the project.
The noise will be louder than the model indicates because, if most of
the flights are to the southwest, many of flights will occur with a tailwind,
the transportation of freight is heavier and causes the aircraft to remain
lower for longer periods of time, and the FAA used an outdated noise model
that does not adequately consider noise emitted from the rear of an aircraft
during takeoff.
Finally, the FAA averaged FedEx's operations with the rest of PTIA’s
operations that occur 24 hours per day, 365 days per year.
However, FedEx’s operations will occur in two short time periods
during the night and only on Monday through Friday.
The FAA therefore drastically underestimated the effect on nearby
residents while they are attempting to sleep.
6. The
FAA’s air quality analysis violated NEPA and the AAIA because it made no
attempt to disclose the impacts from toxic air emissions.
The FAA arbitrarily concluded that there is no correlation between
toxic air emissions and human health.
7. The FAA
violated NEPA and the AAIA because it did not analyze consequences from the
growth that this project will induce. The
FAA states that this project will have economic benefits since it will create
thousands of jobs and notes that this will mean that thousands of people will
move to the area. However, the
FAA does not analyze the environmental consequences from such an increase in
population.
ARGUMENT
I
STANDARD
OF REVIEW
NEPA and the AAIA do not provide for a private right of action.
Therefore, courts review agency decisions challenged under them
pursuant to the Administrative Procedure Act, 5 U.S.C. 551, et
seq. See Sierra Club v. Slater, 120 F.3d 623, 630-631 (6th Cir. 1997); Dubois
v. USDA, 102 F.3d 1273, 1284 (1st Cir. 1996).
The APA provides that a court shall (5 U.S.C. 706):
(2)
hold unlawful and set aside agency action, findings, and conclusions
found to be–
(A)
arbitrary, capricious, an abuse of discretion, or otherwise not in
accordance with law * * *.
An agency’s decision is arbitrary and capricious if (Motor
Vehicle Manufacturers Ass’n v. State Farm Mutual Automobile Insurance Co.,
463 U.S. 29, 43 (1983)):
the
agency has relied on factors which Congress has not intended it to consider,
entirely failed to consider an important aspect of the problem, offered an
explanation for its decision that runs counter to the evidence before the
agency, or is so implausible that it could not be ascribed to a difference in
view or the product of agency expertise.
Accord,
Hughes River Watershed Conservancy v.
Johnson, 165 F.3d 283, 287-288 (4th Cir. 1999).
In reviewing agency decisions under NEPA, courts must ensure that the
agency has taken a “hard look” at the consequences of its proposed action.
Kleppe v. Sierra Club, 427
U.S. 390, 410, n. 21 (1976). This
requires that courts “engage in a ‘substantial inquiry’ to determine
‘whether there has been a clear error of judgment.’”
Conservation Council v. Froehlke,
473 F.2d 664, 665 (4th Cir. 1973) (quoting Citizens
to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 416 (1971)).
While the court should not “substitute its judgment for that of the
agency,” a court’s inquiry into the facts is to be searching and careful.
Hughes River Watershed
Conservancy v. Johnson, supra,
165 F.3d at 288. NEPA
“prohibits uninformed – rather than unwise – agency action.”
Robertson v. Methow Valley
Citizens Council, 490 U.S. 332, 351 (1989).
“Nevertheless, the agency must examine the relevant data and
articulate a satisfactory explanation for its action including a ‘rational
connection between the facts found and the choice made.’”
Motor Vehicle Manufacturers
Ass’n, supra, 463 U.S. at 43.
II
STATUTORY
BACKGROUND
“NEPA expresses a strong federal policy in favor of preserving the
natural environment * * *.” Ely v. Velde, 451
F.2d 1130, 1132, n. 4 (4th Cir. 1971). Section
101, 42 U.S.C. 4331, provides:
The
Congress, recognizing the profound impact of man’s activity on the
interrelations of all components of the natural environment, particularly the
profound growth, high-density urbanization, industrial expansion, resource
exploitation, and new and expanding technological advances and recognizing
further the critical importance of restoring and maintaining environmental
quality to the overall welfare and development of man declares that it is the
continuing policy of the Federal Government * * * to use all practicable means
and measures * * * in a manner calculated to foster and promote the general
welfare, to create and maintain conditions under which man and nature can
exist in productive harmony, and fulfill the social, economic, and other
requirements of present and future generations of Americans.
Thus,
Congress has “declare[d] a broad national commitment to protecting and
promoting environmental quality.” Robertson,
supra, 490 U.S. at 348.
“To ensure that this commitment is infused into the ongoing programs
and actions of the Federal Government, the act also establishes some important
‘action-forcing’ procedures” (citations omitted).
Robertson v. Methow Valley Citizens Council, supra, 490 U.S. at 348. NEPA
requires “that federal agencies prepare EISs to be included ‘in every
recommendation or report on proposals for . . . major Federal actions
significantly affecting the quality of the human environment’” (omission
in original). Hughes River Watershed Conservancy v. Glickman, 81 F.3d 437, 443
(4th Cir. 1996), appeal after remand sub
nom. Hughes River Watershed
Conservancy v. Johnson, supra.
“Major Federal action” encompasses “new and continuing
activities, including projects and programs entirely or partly financed,
assisted, conducted, regulated, or approved by federal agencies * * *.”
40 C.F.R. 1508.18(a).
The EIS requirement serves the Act’s action-forcing purpose in two
respects. First, it “ensures
that the agency, in reaching its decision, will have available, and will
carefully consider, detailed information concerning significant environmental
impacts * * *.” Robertson
v. Methow Valley Citizens Council, supra, 490 U.S. at 349.
Second, it “guarantees that the relevant information will be made
available to the larger audience that may also play a role in both the
decisionmaking process and the implementation of that decision.”
Ibid.
Thus, “by focusing the agency’s attention on the environmental
consequences of a proposed project, NEPA ensures that important effects will
not be overlooked or underestimated only to be discovered after resources have
been committed or the die otherwise cast” (citations omitted).
Ibid.
In order to implement NEPA’s provisions, Congress created the Council
on Environmental Quality (“CEQ”). 42
U.S.C. 4342. CEQ has promulgated regulations implementing the Act.
See 40 C.F.R. 1500, et
seq. These regulations “are
binding on all federal agencies, and CEQ’s interpretation of NEPA is
entitled to substantial deference.” Sugarloaf Citizens Ass’n v. Federal Energy Regulatory Commission,
959 F.2d 508, 512, n. 3 (4th Cir. 1992) (citing Andrus v. Sierra Club, 442 U.S. 347, 357-358 (1979)).
While NEPA and its regulations “establish[] environmental quality as
a substantive goal,” they do not require substantive results.
Hughes River Watershed Conservancy v. Glickman, supra,
81 F.3d at 443. Instead, they set
“forth procedures that agencies must follow.”
Ibid.
However, these “are not highly flexible. Indeed, they establish a strict standard of compliance.”
Calvert Cliffs’ Coordinating
Committee, Inc. v. United States Atomic Energy Commission, 449 F.2d 1109,
1112 (D.C. Cir. 1971). Accord,
Ely v. Velde, supra, 451
F.2d at 1138.
It is through NEPA’s action-forcing procedures that Congress intended
to “affect the agency’s substantive decision.”
Robertson v. Methow Valley Citizens Council, supra, 490 U.S. at 350. Writing
for the Court of Appeals for the First Circuit, then-Judge Breyer explained (Massachusetts
v. Watt, 716 F.2d 946, 952 (1st Cir. 1983)):
NEPA
is not designed to prevent all possible harm to the environment; it foresees
that decisionmakers may choose to inflict such harm, for perfectly good
reasons. Rather, NEPA is designed to influence the decisionmaking process; its
aim is to make government officials notice environmental considerations and
take them into account.
The AAIA, 49 U.S.C. 47101, provides in relevant part:
(a)
It is the policy of the United States–
* * *
(4) that appropriate provisions should be made to make the
development and enhancement of cargo hub airports easier;
* * *
(6)
that airport development projects under this subchapter provide for the
protection and enhancement of natural resources and the quality of the
environment of the United States * * *.
The AAIA also provides that
the FAA may approve an airport project (49 U.S.C. 47106(c)(1)(C)):
if the application is found to have a significant adverse effect on
natural resources, including fish and wildlife, natural, scenic, and
recreation assets, water and air quality, or another factor affecting the
environment, only after finding that no possible and prudent alternative to
the project exists and that every reasonable step has been taken to minimize
the adverse effect.
III
THE FEIS’S PURPOSE AND NEED ANALYSIS DOES NOT COMPLY WITH NEPA
An EIS’s statement of purpose and need must “briefly specify the
underlying purpose and need to which the agency is responding in proposing the
alternatives including the proposed action.”
40 C.F.R. 1502.13.
A.
THE FAA’S ANALYSIS OF THE NEED FOR THE PROJECT CONTAINS INACCURATE DATA
AND INCORRECT ASSUMPTIONS
Where an agency’s conclusions are based on false premises or
information, its decision is arbitrary and capricious.
Van Abbema v. Fornell, 807 F.2d
633, 639 (7th Cir. 1986). Accord,
Sierra Club v. United States Army Corps of
Engineers, 701 F.2d 1011, 1030 (2d Cir. 1983) (an EIS that contains false or
inaccurate statements fails to “provide the basis for an informed evaluation
or a reasoned decision”). The use
of inaccurate information “may result in approval of a project that otherwise
would not have been approved because of its adverse environmental effects.”
Hughes River Watershed Conservancy
v. Glickman, supra, 81 F.3d at
446.
The FAA determined the purpose and need for this project based on four
conclusions: (1) the minimum length
of runway needed for FedEx’s operations is 9,000 feet; (2) FedEx requires two
runways of this length; (3) the runways must be parallel to allow the use of
head-to-head operations (landing from one direction and taking off towards the
same direction); and (4) the sorting facility must be situated in the middle of
the two runways. See
FEIS, pp. 2-6 to 2-15.* These
conclusions are based on both inaccurate data and unsupported assumptions.
1. Minimum
Runway Length
According to the FAA, a particular aircraft will dictate the minimum
runway length needed if that aircraft is expected to perform 250 annual
departures or 500 annual operations.[7] FEIS,
p. 2-7.* This aircraft is known as the “critical aircraft.”
Ibid.
Here, the FAA states that the critical aircraft is a DC-10 that will be
making one daily departure from PTIA to San Juan, Puerto Rico.
Ibid.* Based on the
weight of a DC-10 carrying enough fuel to reach San Juan (1,760 nautical miles)
and a full load of freight, the FAA concluded that a minimum runway length of
9,000 feet was required. Ibid.* Although the
FEIS does not discuss the minimum runway length necessary if a DC-10 were not
the critical aircraft, the majority of the proposed operations are expected to
travel only between 500 and 1,000 nautical miles. Ibid.*
The FEIS does not contain FedEx’s schedule of operations and it is not
clear that FedEx ever provided it to the FAA.
Instead, it appears that the FAA assumed that, since FedEx would be
conducting operations Monday through Friday, the DC-10's trip to San Juan would
occur 260 times per year (5 days x 52 weeks), thereby necessitating the
9,000-foot runway. See
FEIS, p. 2-7.* However, FedEx’s
preliminary schedule shows that while five DC-10's will be used, they will fly
only Monday through Thursday.[8]
Ex. 17, p. 2.* Since only one of these planes will be flying to Puerto Rico
(FEIS, p. 2-7*), there will be at most 208 annual departures by DC-10's to that
destination. Under the FAA’s
guidelines, this cannot be the “critical aircraft” for determining the
minimum runway length. Accordingly,
the FAA arbitrarily concluded that FedEx’s operations require a 9,000-foot
runway.
2. Need
for Two Runways
Even if a 9,000-foot runway were needed, PTIA already has a runway that
is 10,001 feet long (runway 5/23). FEIS,
p. 2-7.* The evidence does not support the FAA’s conclusion that two
9,000-foot runways are necessary.
According to the FAA, “a second minimum 9,000-foot runway is needed to
prevent interruption of aircraft operations due to runway closures.”
FEIS, p. 2-7.* The FAA
supports this statement with two tables showing that between 1988 and 1999 there
have been a total of 790 runway closures for maintenance, amounting to 1,305
hours of closure, and 293 incidents, amounting to 129.47 hours of closure. FEIS, tables 2.2-1, 2.2-2.*
However, this information is not divided between PTIA’s two runways, so
it is not disclosed how often the 10,001-foot runway is closed.
Moreover, the FAA makes no argument (and presents no data) that the
closures have caused any delays. Thus,
the data presented in tables 2.2-1 and 2.2-2 do not support the FAA’s
contention that a second runway is needed.
Furthermore, the FAA acknowledges that runway maintenance could be done
during the daytime when none of the cargo hub operations would occur.
FEIS, p. 2-8.* The FAA also
admits that routine maintenance could take place on the weekends, particularly
weekend nights when there would be minimal regular operations and none of the
cargo hub operations. Ibid.; Ex. 11.* Thus,
the record indicates that maintenance can occur without interrupting the cargo
hub’s operations. As a result,
there is no reason to assume that the lack of a second 9,000-foot runway would
affect the single flight to Puerto Rico, let alone other FedEx operations.
3. The
Runways Must Be Parallel
Even if the FAA had properly concluded that two 9,000-foot runways are
required, the record does not support FAA’s conclusion that two parallel
runways providing for the use of head-to-head operations is required.
Instead, the record shows that the current, perpendicular configuration
would satisfy FedEx’s need (and even more so if existing runway 14/32 were
extended to 9,000 feet).
According to the FAA’s capacity analysis, PTIA’s current
configuration has a total capacity of 1,224 operations per day.
This is based on a weighted hourly capacity of 51 per hour (24 x 51).
See FEIS, p. 2-10.*
In 1998, PTIA averaged only 350.76 operations per day.
Id., table 4.2.5-2.[9]* By
2006, if this project is built, PTIA is expected to average 418.8 operations per
day. Id.,
table 5.1.2-4.* This is only 34
percent of PTIA’s current daily capacity.
By 2019, PTIA is expected to average 575.8 operations per day (id., table 5.1.2-5*), only 47 percent of PTIA’s current daily
capacity.
The extra capacity of the existing airport is even clearer when
operations at PTIA are broken down by hour.
PTIA averages only 5.1 operations per hour between 10:00 PM and 7:00 AM
(Ex. 13*), when all of FedEx flight operations will occur (FEIS, p. 5-10*).
This means that FedEx would have almost complete access to the existing
runways during its operating hours.
The FAA’s traditional capacity analysis, the Annual Service Volume
(“ASV”) calculation, also shows that PTIA’s current configuration would
satisfy FedEx’s operational needs. According
to the FEIS, “ASV is the FAA’s standard method of estimating an airport’s
'theoretical' annual operational capacity for the 20-year planning horizon.”
FEIS, p. 2-9.* Under the
FAA’s guidelines, an airport should take action to improve its capacity when
it is operating at 80 percent of its ASV. Id.,
p. 2-10.*
Without the cargo hub, the FAA predicts that PTIA’s operations will
exceed 80 percent of its ASV in 2019. FEIS,
table 2.2-3.* With the cargo hub,
the FAA predicts that PTIA’s annual operations will exceed 80 percent of its
ASV in 2009. Ibid.
Thus, capacity improvements would be required at that time.
It is questionable whether there is a present need to build a third
runway when it is not needed for at least another seven years.
In any event, the FAA’s ASV analysis contains two errors which
accelerated by 10 years the date when improvements will be needed.
First, the ASV calculations are premised on the assumption that PTIA’s
weighted hourly capacity is 51.[10] This
was derived from the assumption that PTIA currently has an hourly capacity of 62
operations during good weather (visual flight rules - “VFR”) and 46 during
bad weather (instrument flight rules - “IFR”).
R. 78, p. 3.* However, in
PTIA’s 1998 proposal to solicit FedEx’s business, PTIA stated that its VFR
hourly capacity is 76 and its IFR hourly capacity is 59.
Ex. 15, p. AU002166.* Similarly,
PTIA’s December 1994 Master Plan Update states that its VFR hourly capacity is
77 and its IFR hourly capacity is 56. Ex.
44, p. 5-8.* Based on the lower
values of these figures (76 for VFR and 56 for IFR), PTIA has a weighted hourly
capacity of approximately 62.[11]
This hourly capacity dramatically increases PTIA’s ASV (i.e.,
its capacity) for all years. For
example, in 2019, the ASV jumps from 198,594 to 241,428.
Second, the FAA’s estimate of the PTIA’s annual operations with the
cargo hub is too high. According to the FEIS (table 2.2-3*), there will be 169,674
annual operations in 2019 without the cargo hub. With the hub, this number increases to 202,434.
Ibid.
The difference is due to the assumption that there will be an additional
126 daily FedEx operations, 260 days per year.[12]
However, as noted above (p. 4), FedEx currently conducts 26 operations
and, if the hub is built, will increase that by another 100 (not 126)
operations. Id.,
table 1.3-1 and n. 2.* Therefore,
the estimate of 2019 operations should have been 195,674.[13]
Using the adjusted figures for PTIA’s 2019 annual operations and 2019
ASV, with the development of the hub, the level of PTIA’s annual operations
does not reach 80 percent of its ASV until 2019 – ten years later than the
date predicted by the FEIS.[14] Thus,
under the FAA’s standard capacity analysis, improvements with the hub are not
needed for another 17 years.
The FAA admits that the “ASV calculation taken by itself does not
demonstrate an immediate need to construct a third runway at PTIA based on
capacity.” FEIS, p. 2-10.* See also Ex. 16*
(the FAA admits that PTIA “is operating at significantly less than its annual
capacity”). However, the FAA
maintains that the current, perpendicular configuration is insufficient for this
project because it cannot meet the “unique operational characteristics” of
FedEx’s operations. FEIS, p.
2-10.*
According to the FEIS (p. 2-9*):
The
existing two-runway layout at [PTIA] precludes dual simultaneous independent
runway use and efficient use of a head-to-head operation scenario.
Without the ability to support dual simultaneous independent operations
and efficient head-to-head operations, [the Airport Authority] concluded that it
could not provide the airfield capacity to satisfy air cargo hub requirements.
In
other words, FedEx must use head-to-head operations and since the current,
perpendicular configuration cannot support such operations, a third runway is
necessary.[15]
Head-to-head operations are a type of operating scenario where “all
landing aircraft arrive from a single direction, and all subsequent departing
aircraft take off to that same direction.”
FEIS, p. 2-12.* This is in contrast to traditional operations where
“arriving aircraft land to one direction, and departing aircraft take off to
the opposite direction.” Ibid. According to the
FEIS (ibid.*):
The
use of [head-to-head operations] is highly restrictive because it is difficult
to integrate other aircraft with other directional requirements into the air
traffic pattern. The head-to-head
flow is rarely used at most airports because it does not typically support
efficient arrival and departure streams into and out of controlled airspace.
Since mixing head-to-head aircraft flows with “traditional” aircraft
flows creates difficulties for air traffic controllers, * * * it is desirable to
use either head-to-head or traditional, but not both, at any given time.
Here, the FEIS says that head-to-head operations are necessary in order
to meet FedEx’s critical, minimum departure-time requirements.
FEIS, p. 2-11.* The FEIS
states that FedEx must be able to have all of its aircraft depart within 70
minutes. Ibid.*
Thus, by 2019, 63 aircraft must be able to depart within 70 minutes.
Ibid.
However, as noted above (pp. 4-5), the FEIS's discussion concerning
FedEx’s operations indicates that Phase 2 arrivals will occur between 10:00 PM
and 2:00 AM and the departures will occur between 4:00 AM and 7:00 AM.
FEIS, p. 5-10.* This is also confirmed by FedEx’s preliminary flight
schedule which indicates that most flights will occur between 11:00 PM and 5:00
AM. Ex. 17, p. 2.* In fact, according to this schedule, the highest number of
departures in any given 70-minute period is 16 (2:55 AM to 4:05 AM).
Ibid.
Thus, the record is devoid of any explanation as to why FedEx must be
able to have all 63 of its aircraft depart within 70 minutes.
Moreover, even if such a 70-minute requirement existed, the current
configuration could meet it. As
discussed above (pp. 22 - 23), PTIA’s hourly capacity, in good weather, is
between 62 and 77 operations and, in bad weather, between 46 and 56 operations.
These numbers translate into 72 and 90 operations per 70 minutes in good
weather and 54 and 65 operations per 70 minutes in bad weather.
PTIA experiences good-weather conditions 85 percent of the time.
FEIS, p. 2-10.* Thus, even
if all 63 of FedEx’s departures and arrivals had to occur within 70 minutes,
the record shows PTIA can meet the 70-minute requirement in good and bad weather
(assuming the higher value for PTIA’s hourly capacity in bad weather). The worst case scenario would be that PTIA could not meet
that requirement 15 percent of the time (assuming the lower value for PTIA’s
hourly capacity in bad weather).[16]
Similarly, the evidence indicates that the use of head-to-head operations
is not an operational requirement. The
FEIS states (p. 2-12*) that, according to FedEx, “it requires the head-to-head
scenario to operate efficiently and at full capacity in its unique
environment.” The FAA apparently
accepted this statement at face value without any independent assessment.
FedEx employs a “hub system.” Pl.
Ex. 18, p. AU001949.* Under this
system, FedEx has a “superhub” in Memphis, national hubs in Indianapolis,
Fort Worth and Anchorage, and regional hubs in Newark and Oakland.
Id., pp. AU001949-AU001950.*
In order to conduct head-to-head operations on parallel runways, the
runways must be at least 3,400 feet apart.
FEIS, p. 3-22.* However, maps of the airports containing FedEx’s hubs show
that only Memphis and Indianapolis have parallel runways that are sufficiently
separated to support head-to-head operations.
See Ex. 19, pp. 1-2, 10-11.*
At Fort-Worth Alliance Airport, the runways are approximately 600 feet
apart (Ex. 19, p. 3*); at Newark, the runways are approximately 1,000 feet apart
(id., pp. 6-7*); at Oakland, the
runways are approximately 1,000 feet apart (id.,
pp. 8-9*); and at Anchorage, the runways are less than 1,000 feet apart (id.,
pp. 4-58*). Thus, at
most, FedEx can operate head-to-head operations at two of its six cargo
hubs. There is no reason to assume
that FedEx actually conducts head-to-head operations even at those airports
since such operations are “highly restrictive” and rarely used.
See p. 25 above.
Petitioner Gil Happel, a veteran pilot with U.S. Airways, states that
“[f]rom my trips to Indianapolis, I know that FedEx seldom uses more than one
runway.” Ex. 32, para. 5.*
The only discussion in the FEIS supporting the need for head-to-head
operations at PTIA involves a Total Airport and Airspace Modeling (“TAAM”)
analysis. See
FEIS, p. 2-10 to 2-11;* R. 130. The
TAAM analyzed four alternatives for FedEx’s operations:
(1) maintaining the current configuration but using only runway 5/23; (2)
maintaining the existing configuration and using both runways, 5/23 and 14/32;
(3) maintaining the current configuration but expanding runway 14/32 to 9,000
feet and using both runways; and (4) building a 9,000-foot runway parallel to
runway 5/23. R. 130, pp. 6-7.[17]* In
all scenarios, the sorting facility was located in the same place, on the
northeastern end of the runway airport, adjacent to runway 5/23.
Ibid.
The FEIS claims that the TAAM analysis was intended to answer whether
“the existing two runway airfield layout at PTIA [could] accommodate the
nighttime operational requirements associated with the proposed air cargo
hub.” FEIS, p. 2-11.*
However, the TAAM analyzed only which configuration would result in the
least amount of delay for FedEx and therefore would save FedEx the most money.
R. 130, p. 8.* The TAAM
concluded that “Alternative 4 gives the best results as far as on time
planning factors are concerned.” Id.,
p. 9.* See also id., pp.
41-42.*
The TAAM never addresses whether the other alternatives have sufficient
capacity to enable FedEx to conduct all of its operations within 70 minutes, let
alone within 3 or 4 hours. The TAAM
also does not indicate that any of the other alternatives would be
cost-prohibitive. Moreover, since the proposed sorting facility is located at
the northeastern end of the airport in all of the alternatives, rather than at
the southeastern end where it could be located (see
FEIS, pp. 3-26 to 3-27*), the third alternative would unnecessarily require
FedEx’s aircraft to taxi over a mile and one half to reach runway 14/32.
R. 130, p. 7.* Nonetheless, despite this configuration, the TAAM shows that
this alternative will result in only slightly more delays than the parallel
runway-configuration, especially with respect to departure delay, which is the
critical component to FedEx’s alleged 70-minute requirement.
Id., pp. 41-42.[18]*
In sum, the FAA’s standard method (ASV calculation) of evaluating
whether an airport is ripe for expansion indicates that PTIA need not do so
until 2019. Therefore, in order to
attempt to show that parallel, 9,000-foot runways are presently necessary, the
FAA deviated from this method and
imposed a 70-minute departure requirement for all aircraft.
However, the record shows that the FAA's conclusion relied on misleading
data and made incorrect assumptions. Since
the FAA deviated from its traditional method of determining whether capacity
improvements are required, petitioners submit that it is particularly important
that this Court require the FAA to do an accurate analysis.
Moreover, the FAA has shown only that head-to-head operations on parallel
runways would save the most time and money for FedEx.
Petitioners have no reason to doubt that that is true since it is what
FedEx wants and FedEx has stated that, without it, it will look to other
airports to develop its Mid-Atlantic Hub. R.
163, p. 3.* However, where the
project also involves the expenditure of $108,000,000 in federal taxpayer
dollars, taking numerous private properties, severe harm from noise to nearby
residents, noxious emissions, and destruction of 23.8 acres of wetlands and
13,917 linear feet of streams (ROD, p. 66*), NEPA requires the agency to weigh
the economic benefit of the project against the environmental and other costs.
Hughes River Watershed Conservancy
v. Johnson, supra, 165 F.3d at
289. This mandates a thorough,
detailed analysis that is provided to the public in the EIS. Natural Resources
Defense Council, Inc. v. Morton, 458 F.2d 827, 833 (D.C. Cir. 1972).
The FAA’s failure to provide accurate information in the FEIS
concerning the need for the project violates NEPA.
B.
THE FAA DEFINED THE PURPOSE OF THE PROJECT TOO NARROWLY
The definition of the project’s purpose necessarily dictates the range
of alternatives that the agency will consider.
Therefore, “an agency cannot define its objectives in unreasonably
narrow terms.” Carmel-by-the-Sea v.
DOT, 123 F.3d 1142, 1155 (9th Cir. 1997).
The purpose of this project should have been defined as developing a
Mid-Atlantic cargo hub. That is
what FedEx sought to do when it solicited bids from airports in North and South
Carolina. See pp. 7-8 above.
However, according to the FAA, the “purpose and need for the proposed
project is to develop facilities at PTIA that would provide airside, landside,
and surface transportation improvements to support the development and efficient
operation of an overnight, express air cargo hub facility at PTIA.”
FEIS, p. 2-16.* As we will
discuss below, this narrow view of the project, the construction of a hub at
PTIA, allowed the FAA to eliminate from serious consideration reasonable and
feasible alternatives at other sites.
IV
THE
FEIS’S ANALYSIS OF ALTERNATIVES DOES NOT
COMPLY
WITH NEPA OR THE AAIA
An EIS must contain a detailed statement of the “alternatives to the
proposed action.” 42 U.S.C.
4332(B)(iii). CEQ’s regulations
provide (40 C.F.R. 1502.14):
This
section is the heart of the environmental impact statement.
* * * [I]t should present
the environmental impacts of the proposal and the alternatives in comparative
form, thus sharply defining the issues and providing a clear basis for choice
among options by the decisionmaker and the public.
In this section agencies shall:
(a)
Rigorously explore and objectively evaluate all reasonable alternatives *
* *,
(b)
Devote substantial treatment to each alternative considered in detail
including the proposed action so that reviewers may evaluate their comparative
merits; * * *.
“The range of alternatives that an agency must consider is not
infinite, of course, but it does include all ‘feasible’ or ‘reasonable’
alternatives to the proposed action.” Grapevine v. DOT,
17 F.3d 1502, 1506 (D.C. Cir. 1994). The
“existence of a viable but unexamined alternative renders an [EIS]
inadequate” (internal quotations and citation omitted).
Idaho Conservation League v. Mumma,
956 F.2d 1508, 1519 (9th Cir. 1992). Accord,
Dubois v. USDA, supra, 102
F.3d at 1287.
Petitioners submit that the FAA’s alternatives analysis does not comply
with NEPA and the AAIA because the FAA failed to consider in detail even a
single off-site alternative and because the FAA failed to consider, except for
the No-Action Alternative, any on-site alternative that did not involve the
construction of a second, parallel 9,000-foot runway.
The FEIS’s alternatives analysis has two levels.
At the first level, the FAA eliminated any alternative that would not
meet “the purpose and need criteria.” See
FEIS, p. 3-3 to 3-8.* At the second
level, it considered the constructability, costs, and environmental impacts of
the remaining alternatives.
Five build alternatives survived the first-level:
Alternatives W1-A1 (the preferred alternative), W2-A, W3-A, N-D, and N-E. FEIS, p. 3-34.* These
five alternatives also survived the second level and therefore were considered
in detail along with the No-Action Alternative. Id., p. 3-41.*
The only differences among these alternatives are the direction of the
parallel, 9,000-foot runways and the location of the sorting facility.
See id.,
figure 3.3.2-1, pp. 3-22 to 3-26.* Thus,
the FEIS did not seriously consider any build-alternative other than the
construction of a new 9,000-foot runway at PTIA.
A.
THE NARROWLY DEFINED PURPOSE RESULTED IN THE IMPROPER ELIMINATION OF
REASONABLE, OFF-SITE ALTERNATIVES
As noted above, the FAA defined the purpose of this project as developing
a cargo hub at PTIA. Nonetheless, the FEIS claims that “off-site * * *
alternatives were developed and explored which could meet the purpose and need
for this project * * *.” FEIS, p.
3-1.* Despite this claim, when the
FAA screened these alternatives under the purpose and need criteria, every
off-site alternative was summarily rejected because it was not PTIA.
The five airports which submitted proposals to serve as FedEx’s
Mid-Atlantic hub, namely Global Transpark, Raleigh-Durham International Airport,
Charlotte International Airport, Greenville-Spartanburg International Airport,
and Columbia International Airport, constitute obvious off-site alternatives.
The FEIS briefly addresses them but concludes that none meets the purpose
and need criteria, because each airport “does not locate the hub at PTIA.”
FEIS, pp. 3-18 to 3-20.*
The Global Transpark (“GTP”) is envisioned to be “a facility where
industry assembles, stockpiles, and delivers goods for quick distribution
through a huge airport facility that is linked by interstate quality highways to
the rest of the Southeast.” Ex. 23, p. 2.* GTP’s
Master Plan calls for two parallel runways of 11,500 and 13,000 feet.
Ex. 22, p. 6.* This facility was located at Kinston because of the “need
for a commercial distribution hub in the Eastern United States that can reach
overnight more than 60 percent of the nation’s population * * *.”
Id., p. 3.*
Thus, this airport was developed for the very purpose of providing a site
for operations such as those proposed by FedEx.
The FAA rejected GTP for two reasons:
(1) it is not PTIA and (2) it is 30 miles from a major highway.
FEIS, p. 3-18.* If the first
reason is valid, there clearly is no point in discussing this alternative, or
any off-site alternative. With
respect to the FAA’s second reason, while GTP may be 30 miles from an
interstate highway, it is located approximately 5 miles from U.S. Highway 70, a
National Highway System road. Such
a road is “important to the nation’s economy, defense and mobility.”
Ex. 21, p. 1.* By the end of
2001, the State was expected to have completed the “Crescent Connector” in
order to allow direct access from U.S. 70 to GTP. Ex. 22, p. 8.* “[T]his
corridor will feature multi-lane access, separated turning lanes with upgraded
intersections, grade separated railroad crossings and signal systems to handle
increased traffic flows.” Id.,
p. 9.* Moreover, GTP involved the expenditure of over $100,000,000
in planning and development by a “team of nationally and internationally
recognized professionals.” Id.,
p. 6; Ex. 23, p. 2.* They
undoubtedly considered the surrounding road system in their efforts to create
the ideal facility for integrating “air, rail, road, and nearby sea
transportation.” Ex. 22, p. 1.*
Accordingly, petitioners submit that GTP was a viable alternative that
the FAA was required by NEPA and the AAIA to consider.
Similarly, the FAA improperly dismissed from detailed consideration
Raleigh-Durham International Airport (“RDU”).
RDU currently has parallel runways.
FEIS, p. 3-18.* The runways are 10,000 feet and 7,500 feet long and they are
sufficiently spaced to allow for head-to-head operations.
Ibid.
The FAA dismissed RDU for three reasons:
(1) it is not PTIA; (2) it does not have redundant 9,000-foot runways;
and (3) there is no room to place a sorting facility between the two runways
without relocating existing facilities. FEIS,
p. 3-18.* None of these reasons
justifies exclusion from detailed consideration.
In order to have redundant 9,000-foot runways, RDU would only have to
extend its 7,500-foot runway by 1,500 feet, obviously a much smaller project
than building a completely new runway as is being proposed at PTIA.
In addition, as we showed above (pp. 18-19), it is not clear that even a
single 9,000-foot runway is necessary, let alone two 9,000-foot runways.
It also is not clear that the sorting facility must be located between
the two runways since FedEx’s superhub in Memphis does not have that
configuration. Ex. 19, p. 2.*
Moreover, the FEIS does not discuss how extensive a project it would be
to relocate some of the existing facilities at RDU and put FedEx’s facility in
between the runways.
Charlotte/Douglas International Airport (“CLT”) currently has two
parallel runways of 8,845 and 10,000 feet and a crosswind runway.
FEIS, p. 3-20.* The parallel
runways are sufficiently spaced to permit head-to-head operations.
Ibid.
In addition, the FAA has approved the construction of a third 9,000-foot
parallel runway. Ex. 24, p. 2.*
Thus, CLT will soon have three parallel runways, two of which are over
9,000 feet and one is nearly 9,000 feet.
The FAA did not consider CLT in detail because:
(1) it is not PTIA and (2) CLT’s existing aircraft operations and noise
abatement requirements would conflict with FedEx’s head-to-head operations.
FEIS, pp. 3-20 to 3-21.*
The FAA does not provide any evidence to support its claim that FedEx’s
nighttime operations would conflict with existing aircraft operations or with
noise abatement requirements. FedEx
manages to operate effectively at numerous other airports that have competing
aircraft operations. See
p. 27 above. Moreover, following the events of September
11, 2001, and the decline in demand for air travel, CLT halted construction on
its improvements. Ex. 25, p. 2.*
This could mean that there would be a new runway available almost
exclusively for FedEx operations. Therefore,
even if a conflict with existing aircraft would have previously been a factor to
consider, there is no reason to assume that this still exists.
Greenville-Spartanburg International Airport (“GSP”) is located only
one mile from a major interstate and currently has one runway of 11,000 feet.
FEIS, p. 3-19.* The FEIS
summarily dismisses GSP because: (1)
it is not PTIA; (2) it would require the construction of a parallel runway; (3)
it would require the relocation of many facilities; and (4) it does not have
enough space in the event that FedEx’s operations grow.
Ibid.
The construction of a parallel runway obviously does not distinguish GSP
from PTIA. The FEIS also does not
discuss how extensive a project it would be to relocate some of the existing
facilities, except to say that it depends on the location of the sorting
facility. Ibid. Finally, the FEIS
states only that “the proposed site for the air cargo hub is too small,”
without providing any more information, and does not indicate whether any site
other than the one GSP proposed to FedEx would be feasible.
Ibid.
Columbia Metropolitan Airport (“CAE”) has two runways, 8,000 and
8,602 feet long, and is located within one mile of a major interstate.
FEIS, p. 3-19.* The FEIS
rejects CAE because: (1) it is not
PTIA and (2) competing aircraft operations would be inconsistent with
head-to-head operations. However,
as noted above (pp. 27-28), the FAA's assumption that head-to-head operations
are essential is erroneous since other FedEx hubs do not operate head-to-head.
In short, the FAA rejected each of these alternatives without significant
analysis simply because it is not PTIA. Other
reasons were given, but these reasons are presented in cursory fashion and are
not persuasive, at least in the absence of analysis.
In fact, FedEx implicitly recognized that these airports are reasonable
alternatives because it stated that it would be forced to consider them if PTIA
does not build the proposed, parallel runway.
R. 163, p. 3.*
The FAA’s contractor and the FAA informed FedEx that they were required
to analyze off-site alternatives and they therefore requested an explanation as
to why these other airports were not viable.
R. 153, p. 2; R. 156, p. 2.* FedEx responded
by setting forth the factors it considered in the selection process and saying
that it rated PTIA the highest in most of them. R. 163, pp. 6-7.* FedEx
refused to provide its own analysis of these airports to the FAA on the ground
that the information was confidential. R.
145, p. 2.* However, NEPA imposes
an independent obligation on the FAA to review this information.
See 40 C.F.R. 1506.5(a)(“The
agency shall independently evaluate the information submitted and shall be
responsible for its accuracy”). Here,
the FAA simply accepted FedEx’s conclusion at face value.
Consequently, the FAA’s rejection of these alternatives was arbitrary
and capricious.
Essentially, the issue here is whether NEPA requires the FAA to analyze
only which is the best way to configure PTIA to carry out FedEx's wishes or
whether NEPA requires the FAA to analyze other reasonable and feasible
alternatives that may accomplish the “underlying purpose and need to which the
agency is responding * * *.” 40
C.F.R. 1502.13. Petitioners submit that based on the express statutory
purpose and the CEQ regulations, NEPA requires the FAA to look beyond the
application presented to it and analyze alternatives that can accomplish the
underlying purpose, namely, to develop a Mid-Atlantic cargo hub. The total failure of the FEIS to conduct any significant
analysis of these alternatives violated probably the most important requirement
of NEPA. See Simmons v. United States
Army Corps of Engineers, 120 F.3d 664, 670 (7th Cir. 1997) (by “focusing
on the single-source idea [for a water supply], the Corps never looked at an
entire category of reasonable alternatives and thereby ruined its environmental
impact statement”); Van Abbema v.
Fornell, supra, 807 F.2d at 638 (“the evaluation of ‘alternatives’
mandated by NEPA is to be an evaluation of alternative means to accomplish the general
goal of an action; it is not an evaluation of the alternative means by which a
particular applicant can reach his goals” (emphasis in original)); Sierra
Club v. Marsh, 714 F. Supp. 539, 577 (D. Me. 1989) (“A project’s
principal goals must override the stated preferences of the applicant for
purposes of NEPA's ‘reasonable alternatives’ analysis”); California ex rel. Van De Kamp v. Marsh, 687 F. Supp. 495, 499 (N.D.
Cal. 1988) (by failing to “evaluate the
alternative of relocating some or all of the air cargo project at nearby
airports,” the Corps violated NEPA); 46 Fed. Reg. 18,026, 18,027
(“Reasonable alternatives include those that are practical or feasible from the technical and economic standpoint and
using common sense, rather than simply desirable
from the standpoint of the applicant”) (emphasis in original).
But see Citizens
Against Burlington, Inc. v. Busey, 938 F.2d 190, 198-199 (D.C. Cir. 1991),
certiorari denied, 502 U.S. 994 (1991).
B.
THE NARROWLY DEFINED PURPOSE RESULTED IN THE IMPROPER ELIMINATION OF
REASONABLE, ON-SITE ALTERNATIVES
The FAA did not analyze in detail whether the cargo hub could be
constructed at PTIA based on its perpendicular configuration and extending
runway 14/32 to 9,000 feet. The
FEIS states that these alternatives (X-A through X-E) would partially meet the
purpose and need criteria because they would locate the project at PTIA, provide
redundant, 9,000-foot runways, and provide a sorting facility that was
rectangular in shape and on 300 acres. FEIS,
pp. 3-28 to 3-29.* However, the
FEIS dismissed all of them from detailed consideration because they would not
provide for the ability to conduct head-to-head operations or locate the sorting
facility between parallel runways. Id., p. 3-29.* The FEIS
then explained, referencing its previous purpose and need analysis, that these
two criteria are essential.
However, as shown above (pp. 27-28), the use of head-to-head operations
on parallel runways does not exist at four of FedEx's six other hubs, it is not
clear that FedEx performs such operations at the two hubs where they are
feasible, and the only map of the other hubs (Memphis) that depicts the location
of the sorting facility shows that it is not located between the two parallel
runways. Therefore, these reasons
do not justify the FAA’s dismissal of these alternatives from detailed
consideration.
In fact, the perpendicular alternatives are similar to the third
alternative analyzed in the TAAM, which was found to be only slightly worse than
the preferred alternative in terms of saving FedEx time.
See p. 29 above. Moreover,
unlike the TAAM’s third alternative, Alternative X-E locates the sorting
facility at the southeastern end of the airport and therefore allows direct
access to both runways which would save more time.
See FEIS, figure 3.3.2-1.*
However, the FEIS does not examine this benefit or even note the
difference between this alternative and the third one in the TAAM analysis.
Even if modifying the present configuration would not meet all of
FedEx’s requirements, the FAA still should have analyzed at least one such
alternative since NEPA requires the FAA to consider reasonable alternatives that
meet only some of the project’s goals. North
Buckhead Civic Ass’n v. Skinner, 903 F.2d 1533, 1542 (11th Cir. 1990); Natural
Resources Defense Council, Inc. v. Callaway, 524 F.2d 79, 93 (2d Cir. 1975).
Accord, Dubois v. USDA, supra, 102
F.2d at 1288 (the use of artificial ponds for snowmaking, instead of a natural
pond, “is not so facially implausible that it can be dismissed out of
hand”); Sierra Club v. Marsh, supra,
714 F. Supp. at 586-587 (alternatives analysis did not comply with NEPA because
agency considered only a two-berth cargo terminal that was expandable to six
berths and not a two-berth terminal that was partially expandable to less than
six berths).
V
THE FEIS’S NOISE ANALYSIS DOES NOT COMPLY WITH NEPA OR THE AAIA
An EIS must discuss “any adverse environmental effects which cannot be
avoided should the proposal be implemented * * *.”
40 C.F.R. 1502.16. The harm
caused by significant noise levels must therefore be considered in an EIS.
Sound is often expressed in decibels (“dBA”).
Ex. 29, p. 5.* When the
overall noise level increases by 10 dBA, a person will perceive a doubling in
the degree of loudness. Id.,
p. 10.* See also FEIS, App. D, p. 2.* Where
one source of sound produces a specific noise level (70 dBA for example), adding
a second source that also produces 70 dBA of noise will increase the overall
noise level by 3 dBA. Ex. 29, p.
7.*
The FEIS presents three types of measurements for disclosing the noise
impacts from FedEx’s operations: the
Day-Night Sound Level (“DNL”),[19]
the Equivalent Sound Level for 9 hours (10:00 PM to 7:00 AM) (“Leq(9)”), and
the Sound Exposure Level (“SEL”). FEIS,
pp. 5-4 to 5-7.*
The “DNL is the metric commonly used to determine impact from aircraft
operations and is the principal metric used by the FAA in determining the
potential noise impacts of air development actions.”
FEIS, p. 5-7.* It shows the noise level of an average, annual day.
ROD, vol. 2, p. 18.* In
other words, it is the average noise level of a 24-hour period, measured over
365 days. Ibid.; FEIS, p.
5-7.* It is measured by adding all
of the sound exposure during the daytime (7:00 AM - 10:00 PM) and all of the
sound exposure during the nighttime (10:00 PM - 7:00 AM). FEIS, p. 5-7.* Ten
dBA are added to the nighttime noises to reflect the fact that since
“community background noise typically decreases about 10 dBA at night,
nighttime noise events sound louder because there is less ambient noise.”
Ibid.
In analyzing the DNL, the FAA generated three noise contours:
one depicting the areas that will experience 75 dBA and higher (the 75
DNL contour), 70 dBA and higher (the 70 DNL contour), and 65 dBA and higher (the
65 DNL contour). See
FEIS, figure 6.2.1-4.*
All persons living within the 70 DNL contour can have their land
purchased by the government. ROD,
p. 45.* Here, that means 53 homes and 126 people.
FEIS, table 5.1.3-3.* All
persons living between the 65 and 70 DNL contours are eligible for sound
insulation. ROD, p. 46.*
This includes 209 homes and 503 people.
FEIS, table 5.1.3-3.*
In addition, under FAA guidelines, when there is an increase of 1.5 dBA
within the 65 DNL contour, the change is considered significant and mitigation
must be considered for those homes. FEIS,
p. 5-15.* If such an increase occurs, the FAA will also consider
mitigation for homes located within the 60 DNL contour if there is an increase
of 3 dBA. Ibid. Here, 163 homes
and 284 people situated within the 65 DNL contour will experience a change of
1.5 dBA, and 452 homes and 1,096 people situated within the 60 DNL contour will
experience a change of 3.0 dBA. FEIS,
table 5.1.3-7.* However, the FEIS
says that the change within the 60 DNL contour is not a significant impact and
the data are provided only “for informational purposes.” Id., n. 2.*
Therefore, no mitigation has been offered to homeowners within the 60 DNL
contour regardless of whether they experience a change of 3 dBA or more.
See ROD, p. 46.*
The Leq(9) is similar to the DNL except that it is the average sound
level of all of the noise events that occur between 10:00 PM and 7:00 AM.
FEIS, p. 5-6.* An Leq can be
done for time periods other than nine hours.
The FAA used an Leq(9) because it “approximates the time span of FedEx
operations at night.”[20]
FEIS, p. 5-7.*
While DNL and Leq(9) are cumulative noise metrics in that they average
noise over time, the SEL measures a single event.
It is used to analyze disturbances with sleep and interferences with
speech. FEIS, p. 5-5.* During a single noise event, sound will vary with time.
Ibid.
However, a single measurement describes “only one dimension of the
noise,” i.e., how loud was it.
Ibid. Two events, each
with identical noise levels, may generate different sound exposures: one very
short and one that remains loud for an extended period of time.
Ibid.
The latter is perceived to be much more disturbing, yet a single
measurement will not reveal this difference.
Ibid.
The SEL is designed to provide a comparison of such different sound
exposures. FEIS, p. 5-5.*
It treats the exposure as if it occurred in one second, i.e.,
“all of the sound that occurs over the entire time of the event is assumed to
occur in one second.” FEIS, p.
5-5.* As a result, louder events
have higher SEL’s than quieter ones and longer events have higher SEL’s than
shorter ones. Ibid.
A.
THE NOISE ANALYSES ARBITRARILY ASSUMED THAT ALL OF FEDEX’S OPERATIONS
WOULD OCCUR TO AND FROM THE SOUTHWEST 95 PERCENT OF THE TIME
In performing all three noise analyses, the FAA assumed that FedEx would
operate head-to-head to and from the southwest 95 percent of the time, i.e.
95 percent of all aircraft would land from and take off towards the southwest.
FEIS, p. 5-11.* This is dramatically different from the current operations at
PTIA which occur to and from the southwest 54 percent of the time and to and
from the northeast 46 percent of the time. Id.,
p. 2-10.* The 95-percent assumption
“results in unusual configurations to the noise contours * * *”
(id., p. 5-11*), indicating
that there will be nearly no impact on the 2,500 people living directly off the
northeastern end of the new runway (runway 5L), some as close as one-half mile (see
FEIS, figure 6.2.4-1*).
There are serious problems with the FAA’s assumption.
First, the record contains no commitment from FedEx that it actually
intends to operate in this manner and neither the Airport Authority nor the FAA
has imposed any such requirement. Instead,
the FAA assumed that 95 percent of FedEx’s operations will be to and from the
southwest because, in doing so, FedEx would be landing towards and taking off
from the sorting facility, which “reduces time on the ground by minimizing
taxi times by aircraft.” FEIS, p.
5-9.* In other words, the FAA believes that it is more efficient to
operate that way; therefore, it assumed FedEx would do so.
The record contains evidence that FedEx insisted on having unrestricted
access to PTIA’s runways. In a letter to the Airport Authority, FedEx stated that,
given “the strategic nature of the Mid-Atlantic Hub, FedEx will require
assurance we can operate unrestricted at [PTIA] on a 24 hour per day 7 days per
week basis and will not be subject to curfews or other interruptions to air or
ground traffic and hub operations.” Ex.
30, p. 2.* In response to this
demand, the Airport Authority stated that it would “not impose any
restrictions” on FedEx, but “FedEx would be required to land from a
southwest direction, and take off in a southwest direction, whenever
possible, in order to minimize the noise impact of FedEx’s flights over
residential developments” (emphasis added).
Ex. 31, p. 4.* However, this
standard is not included in any contract or other document binding on FedEx.
Second, there is no reason simply to assume that FedEx will operate 95
percent of the time to and from the southwest since there are good reasons for
it not to do so. Unless there is a
tailwind,[21] it is often more efficient “for planes to take
off in the direction of their destination, even if that requires that the plane
taxi down to the other end of the runway.”
Ex. 33, para. 4.* This saves
fuel, reduces engine wear, and saves flight time since the aircraft will travel
a shorter distance to its destination. Ibid.; Ex. 1, p. 11.*
In fact, the very analysis on which the FAA relied to show that
head-to-head operations are the most efficient, the TAAM analysis, assumed that
operations occurred, almost evenly, to and from the northeast and southwest.
Specifically, the TAAM assumed that, between midnight and 3:44 AM, all
operations occurred to and from the southwest and, between 3:45 AM and 06:55 AM,
all operations occurred to and from the northeast.[22] R.
130, p. 7.*
Third, several factors may prevent FedEx from conducting head-to-head
operations. Competing air traffic
from private aircraft[23] or from late-arriving commercial aircraft may
make head-to-head operations impossible. See
Ex. 32, para. 3; Ex. 33, para. 3.* In
addition, the 95-percent assumption is premised on the fact that winds moving
southwest will be greater than 10 knots (11 miles per hour) only 5 percent of
the time.[24]
FEIS, p. 5-11.* However, when there is a 7-to-9-knot wind moving southwest, a
pilot may choose for safety reasons to take off into the wind to the northeast.
See Ex. 33, paras. 3-4; Ex. 1, p. 5.*
B.
THE NOISE ANALYSES UNDERESTIMATE THE LIKELY IMPACTS
Even if the 95-percent assumption were reasonable, the FAA's noise
analyses substantially underestimate the noise impacts from FedEx’s
operations.
The noise analysis was performed using the FAA’s Integrated Noise Model
(“INM”). FEIS, p. 5-4.*
The INM normally assumes that there is a headwind.
Ex. 1, p. 7; Ex. 2, p. 28.* Here,
there will undoubtedly be numerous operations with a tailwind if 95 percent of
all operations occur to and from the southwest.
Ibid.
Whenever there is a headwind for landings, there must be a tailwind for
takeoffs and vice-versa.
An aircraft that takes off with a tailwind will remain at a lower
altitude longer since as it will have less air speed, which it needs to climb.
Ex. 2, p. 28.* Therefore,
the aircraft will be closer to the ground and the noise will be greater. Id., pp. 28-29.*
However, the FEIS does not indicate that it adjusted the INM to account
for this fact and the FAA did not respond to petitioners’ comment regarding
this problem. See
ROD, “FP0021," p. 28.* Therefore,
the FEIS has significantly underestimated the noise impacts.
Similarly, it is not clear that the INM factored in the weight of the
cargo. “It is highly unusual for
an FAA-sponsored FEIS not to state clearly what weights and/or trip lengths are
used in the application of the” INM. Ex.
1, p. 6.* However, here, the FEIS did not provide that information.
FedEx’s aircraft will transport freight which is “much denser than
passengers and baggage.” Ex. 1, p. 5.* “Heavier
aircraft lift off further down the runway and climb more slowly than lighter
aircraft.” Ibid. A fully loaded
cargo plane can create 5 to 8 more dBA of noise than a passenger aircraft.
Id., pp. 5-6.*
Since it appears that the FEIS did not factor in the weight of the cargo,
it significantly underestimated the noise that will be generated.
In response to this comment, the FAA stated only that its analysis
considered the different weights of the types of aircraft FedEx will use.
ROD, p. 16.* Notably, the FAA did not say that it considered the heaviness
of the freight.
The noise analyses also substantially underestimated the impacts from
FedEx’s operations because they were produced from an outdated INM.
The FEIS states (p. 5-4*) that it used version 5.2a of the INM which was
“the latest version of the model at the time the EIS was started.”
This is not accurate. The
FAA released version 6.0 in September 1999.
Ex. 2, Attachment 8.* The
FAA released the draft EIS in April 2000, seven months after version 6.0 was
released. While there may not have
been time to run version 6.0 in the draft, there was more than enough time to do
so in the final EIS.[25]
Nonetheless, in response to this comment, the FAA maintained that the
“FEIS uses the most recent version of the” INM.
ROD, p. 16.*
“Accurate scientific analysis * * * [is] essential to implementing
NEPA.” 40 C.F.R. 1500.1(b).
The recent version of the INM more accurately analyzes “the propagation
of sound from planes on the ground.” Ex.
2, p. 27.* When an aircraft is
rolling down a runway prior to takeoff, it emits sound from its engines. Ibid.
Since the FAA assumed that 95 percent of the takeoffs would occur to the
southwest, nearly all of the noise emitted from the engines will begin at the
northeastern end and be propagated in that direction.
This is near the densely populated area which the FEIS indicates will
receive almost no noise impact. See
FEIS, figure 6.2.1-4.* The FAA’s
failure to use the most recent version of the INM resulted in the inadequate
disclosure of noise effects and violated NEPA.
See North Carolina Alliance for Transportation Reform v. DOT, 151 F.
Supp.2d 661, 696 (M.D. N.C. 2001) (use of outdated air emissions model
“prevented decision-makers and the public from more fully understanding the
[project’s] effect on air quality” and therefore violated NEPA”).
C.
THE NOISE ANALYSES DID NOT TAKE INTO ACCOUNT FEDEX’S UNIQUE OPERATIONS
Finally, the noise analyses should have been adjusted to account for
FedEx’s unique operations. As
noted above, the FAA’s traditional noise analysis (the DNL) measures an
airport’s operations over 365 days per year, 24 hours per day.
It “is most useful when the noise does not vary much from day to day *
* *.” Ex. 2, p. 13.* Here,
the only proposed change to PTIA’s operations will occur on 260 days each year
and only between 10:00 PM and 7:00 AM. Therefore,
the DNL dilutes the consequences from these operations by averaging them with
the airports daytime and weekend operations.
For example, the predicted noise level from one takeoff over point 25,
which is off the northeastern end of the new runway (see
FEIS, figure 5.1.3-1*), is sufficient to generate a 65.6 DNL.
Ex. 1, pp. 2-3.* However,
the actual 65 DNL contour does not extend nearly that far because the
measurement is averaged over 24 hours and over 1 year.
See FEIS, figure 6.2.1-4.*
Nonetheless, the residents located in that area “will at times be
exposed to extreme noise for short periods unlike anything they have experienced
or would have ever expected to experience.”
Ex. 2, p. 40.* Overall, petitioners’ expert estimates that the traditional
DNL analysis understates the actual noise from FedEx’s operations by 4.3 dBA.
Ex. 1, p. 2.*
In justifying the need for this project, the FAA deviated from its
traditional capacity analysis because of FedEx’s “unique operational
characteristics.” See
p. 24 above. Based on those same
characteristics, it was equally necessary for the FAA to deviate from its
traditional noise analysis. If
FedEx truly must conduct all of its operations within 70 minutes in the middle
of the night, the FAA should have disclosed to the public the noise that will be
generated during that 70-minute period. At
the very least, the FAA should have disclosed the noise that will be generated
during FedEx’s stated operational periods for arrivals and departures.
This was especially important because Greensboro is not densely populated
and therefore has less background noise levels than those assumed in the FAA’s
DNL analysis. The level of the DNL in a “residential area is closely
related to the population density averaged over an area of at least a few square
miles.” Ex. 2, p. 22.*
As noted above, under the FAA’s DNL model, noise levels that do not
exceed 65 dBA are not considered significant.
However, an area with a DNL 65 dBA is normally found in a community of
approximately 20,000 people per square mile.
Ibid. Greensboro’s
population density is approximately 2,500 people per square mile.
Ibid.
A DNL 55 dBA is normal in Greensboro and the nighttime noise level would
therefore be approximately 45 dBA. Ibid.;
FEIS, p. 5-7.*
If FedEx’s operations increase the nighttime noise level by 10 dBA to
an overall level of 55 dBA, the background noise level of the community will
have doubled. See p. 43 above.
Here, one of the ten sites used for predicting effects from the
operations shows that there is a 10.4 dBA change but the overall noise level
does not exceed 65 dBA. See
FEIS, tables 5.1.7-2, 5.1.7-3; Ex. 2, p. 52.*
However, the number of people or homes impacted is not disclosed under
the FAA’s DNL analysis since it considers impacts only when the overall noise
level exceeds 65 dBA. See Ex. 2, pp. 15-16.*
The FEIS’s two other analyses, the Leq(9) and the SEL, do not
compensate for the deficiencies in the DNL analysis.
In the Leq(9) analysis, the FEIS provides hardly any information.
The entire analysis consists of a table containing generic information
about the Leq(9)’s numerical results and cursory statements concerning that
table. For example, the entire
discussion of the Leq(9)’s Phase 1[26]
analysis of the preferred alternative is (FEIS, p. 5-24*):
Table
5.1.3-4a presents the nighttime equivalent or Leq(9) noise levels at the
specific points for Alternative W1-A1. Under
Phase 1, Alternative W1-A1 would result in Leq(9) noise levels at the specific
points that vary from 28.2 to 69.2 dBA. Noise levels would decrease up to 17.2 dBA at some points,
while increasing up to 11.7 dBA at others when compared to the No-Action.[[27]]
A noise impact analysis should allow a reader “to look at locations on
a map with appropriate graphics and see the change, either directly or by
comparing two maps showing the before and after conditions.”
Ex. 2, pp. 31-32.* The
Leq(9) analysis does not do this. There
are no noise contours or other maps provided which would disclose where noise
changes will occur. No information
is provided as to how many people, homes, and businesses will be affected. Therefore, the cursory information contained in the FEIS’s
Leq(9) analysis does not adequately disclose the impacts from FedEx’s
operations. See
Hughes River Watershed Conservancy v.
Glickman, supra, 81 F.3d at
445-446 (agency’s cursory analysis of zebra mussel infestation violated NEPA).
In addition, the Leq(9) does not add the 10 dBA penalty in order to
account for the fact that nighttime noise levels have dropped by that amount.
See Ex. 1, p. 3.*
Therefore, even the numeric results in the table understate the
consequences from FedEx’s operations.
According to EPA, the Leq(9) analysis “does not provide a totally
accurate view of the additional noise situation, i.e., noisy takeoff and landing
events occurring during a relatively short late-night and early-morning
timeframe.” FEIS, vol. 5, App. O,
“DF0004,” p. 7.* EPA explained
that while “the current information/data is correct for the average daily
situation, [the DNL and Leq(9)] understate[] the noise exposure for an actual
operational day * * *.” Ibid.
In the SEL analysis, the FAA generated SEL 100 dBA noise contours and
informed the public that no more than 10 percent of adults who are exposed to an
arrival or departure producing an SEL of 100 dBA “are likely to be
awakened.” FEIS, p. 5-5.*
However, the SEL analysis does not attempt to provide additional
information beyond the DNL. The FEIS explains that the “100 dBA SEL contour was
selected because it results in a similar degree (or percentage) of affected
populations as the DNL 65 dBA noise contour.”
FEIS, p. 5-5.* Thus, the
FEIS admits that the use of the SEL 100 dBA was not intended to disclose
consequences that might be overlooked from the use of the DNL analysis.
If the FAA had used a lower SEL than 100 dBA, the number of people
awakened would be less than 10 percent.[28]
Ex. 2, p. 6.* However, the population affected would have been much higher
because the SEL contour would extend much farther out from the runway.
Ibid.
Thus, the total affected population would probably be much greater.
Id., p. 25.* These impacts were not disclosed since those affected
individuals do not lie within the 65 DNL contour.
Id., p. 38; FEIS, p. 5-5.*
VI
THE
FEIS FAILED TO ANALYZE WHETHER THERE WOULD
BE
ANY IMPACTS FROM TOXIC AIR EMISSIONS
Airports are among the largest single source emitters of toxic air
pollutants due to an array of emission sources associated with their operation
(i.e., aircraft, motor vehicles, ground support equipment and stationary plant
operations). R. 318 (Piazza DEIS
Comments, pp. 2-3*). Accordingly, in order to disclose the possible effects from
toxic air emissions from this project, the FEIS should have done an emissions
inventory and then performed a health risk assessment.
Id., p. 4.*
According the FAA, it did not do this because based “on information
available in the scientific literature, there is no known ‘cause-and-effect’
between toxic air emissions from planes and health problems around airports.”
FEIS, App. O, part 2, Response 7-3.*
The FEIS does not indicate to what scientific literature it is referring,
and petitioners set forth substantial scientific literature to the contrary,
which the FAA did not refute. See Ex. 4, pp. 1-4; ROD, p. 27.*
For example, EPA conducted a health risk assessment in 1993 which
reported that emissions from aircraft engines were responsible for approximately
10.5 percent of the cancer cases around Chicago’s Midway Airport.
Ex. 4, pp. 1-2.* The FAA
itself has participated in studies of human health risks from toxic air
emissions related to operations at the Santa Monica Airport and at the Los
Angeles Airport. Id., p. 2.*
The former found “cancer risks for individuals living in proximity of
the airport to readily exceed the U.S. EPA’s ‘ample margin of safety’
threshold of one in one million.” Ibid.
The latter stated that impacts from increased emissions of toxic air
pollutants “may include increased cancer risks and non-cancer health
hazards” to people “working, living, recreating, or attending school on or
near the airport.” Ibid.
Accordingly, the FAA’s failure to analyze the potential risks from
emissions of toxic air pollutants associated with this project violated NEPA and
the AAIA.
VII
THE
FEIS FAILED TO ANALYZE ADEQUATELY THE
INDUCED-GROWTH
EFFECTS FROM THIS PROJECT
An EIS’s discussion of environmental effects must include the
project’s indirect effects and their significance.
40 C.F.R. 1502.16(b). Indirect
effects are defined as reasonably foreseeable effects and may include “growth
inducing effects and other effects related to induced changes in the pattern of
land use, population density or growth rate, and related effects on air and
water and other natural systems, including ecosystems.” 40 C.F.R. 1508.8(b).
In discussing the merits of this project, the FEIS estimated that it will
create 16,308 new jobs by 2019, including 2,650 people directly employed by
FedEx and the rest by new businesses that start because of increased cargo
capacity in the area. FEIS, p. 5-103, table 5.4.3-4.*
The creation of these new jobs is expected to result in 10,872 new
households and 25,006 new persons in the area.
Id.,p. 5-103.*
While the FEIS addresses the benefits of this growth, i.e.
the fiscal advantages that this growth will provide for both the regional and
national economy, it does not discuss its adverse environmental impacts.
For example, the FEIS examines increases in demand for potable water and
for the disposal and treatment of wastewater, but this analysis is based only on
the population increases directly associated with the FedEx facility and its
employees. See,
e.g., FEIS, p. 5-148.* The
FEIS does not address water-quality impacts that will result from the additional
13,500 jobs and new households that will come to the area.
Since CEQ’s regulations require such an analysis, the FEIS does not
comply with NEPA and the AAIA.
CONCLUSION
For the foregoing reasons, petitioners request that the Court order the
FAA to rescind the ROD and prepare a new draft EIS which is consistent with NEPA
and the AAIA.
REQUEST FOR ORAL ARGUMENT
Counsel for petitioners respectfully request that the Court hold oral
argument on these issues.
Respectfully
submitted,
BRUCE J.
TERRIS
DEMIAN A.
SCHANE
Terris,
Pravlik & Millian, LLP
1121 12th
Street, N.W.
Washington,
D.C. 20005-4632
(202)
682-2100
Counsel for
Petitioners
May 6, 2002
[1]/ Pursuant to the Rule 30(c) Briefing Order, petitioners have indicated the material that they intend to include in the deferred Joint Appendix by placing an asterisk after the material. Where there is an asterisk after a citation that includes multiple items, all items in the citation will be included.
[2]/ Citations to exhibits refer to the exhibits attached to the comments petitioners submitted to the FAA on December 17, 2001, and are contained in document number 338 in the Administrative Record. Subsequent citations will only be to exhibit number.
[5]/
The runway number correlates to the direction in which the runway is
pointed. For example, 5 stands
for 50 degrees and 23 stands for 230 degrees.
Zero is directly north. Therefore,
a runway numbered 5 points to the northeast (50 degrees from the north).
The other end of the runway, number 23, points to the southwest (230
degrees from the north).
A single runway contains two numbers (5/23) and is treated as two
runways. A takeoff using runway
5 means a takeoff to the northeast. A
takeoff using runway 23 means a takeoff to the southwest.
However, both operations are on the same runway.
They simply occur in opposite directions.
When there are parallel runways, the letters “L” and “R” are used to differentiate between the runways. “L” and “R” stand for left or right and are based on the direction the plane is facing. Thus, a takeoff using 5L means a takeoff towards the northeast using the runway to the pilot’s left.
[8]/ Petitioners obtained a copy of the schedule after it was made public through the proceedings in PTIA v. Urbine, 554 S.E.2d 331 (N.C. Sup. Ct. 2001), certiorari denied, 122 S. Ct. 1438 (2002).
[9]/ PTIA’s total annual operations peaked in 1995 at 112,747. R. 71, p. 4*. PTIA’s total annual operations dropped to 78,051 in 1996 and then to 67,382 in 1997. Ibid. These reductions were primarily caused by the closure of Continental’s hub and a reduction in operations by US Airways. FEIS, p. 1-7.*
[10]/ The ASV calculation is determined by the following equation: (weighted hourly capacity) x (a daily ratio) x (an hourly ratio). R. 78, p. 5.* The same weighted hourly capacity (51) was used by the FAA for every year, but the other two components changed. Id., pp. 4-5.*
[11]/ Petitioners do not have the data to recompute the precise weighted hourly capacity under FAA guidelines. However, this number can be approximated by working backwards. The weighted hourly capacity of 51 can be derived by using a multiplier of 7 for the IFR hourly capacity and a multiplier of 3 for the VFR hourly capacity ((7 x 46 + 3 x 62) ) 10 = 51). Using this method and an IFR capacity of 56 and a VFR capacity of 76, the weighted hourly capacity is 62 ((7 x 56 + 3 x 76) ) 10 = 62).
[15]/ Under FAA guidelines, only parallel runways that are at least 3,400 feet apart can support head-to-head operations. FEIS, p. 3-22.*
[16]/ The FEIS did not analyze whether, if there were such delays, the costs from them would justify the expenditure of $108 million of federal taxpayer money or the condemnation of numerous private properties.
[18]/ It is also significant that the FAA had to keep re-running its model to get the results it desired. See R. 141, p. 1; R. 95, p. 1.*
[20]/ This provides further support for petitioners' argument that the FAA’s capacity analysis, based on a 70-minute period, is arbitrary. See pp. - above.
[21]/ A commercial aircraft can normally take off safely when it reaches an air speed of 186 miles per hour. Ex. 1, p. 10.* Air speed is the speed of the air moving against the aircraft. If there is a 10 mph wind, an aircraft traveling into the wind will be able to take off when its ground speed reaches 176 mph. Ibid. However, when traveling with the wind (tailwind), the aircraft will not have sufficient air speed until its ground speed reaches 196 mph. Ibid. Consequently, planes typically take off into the wind because they can do so faster and need less runway, allowing them more time to abort should something go wrong. Id., pp. 10-11.*
[22]/ The reverse may actually be true since, as noted above (p. , n. ), it appears that the TAAM mislabeled the runways.
[24]/ When a tailwind is greater than 10 knots, it is not safe for a plane to take off in that direction. FEIS, p. 5-11.*
[25]/ By contrast, the FEIS used the latest version (released in 2000) of the model for assessing noise from vehicular traffic. Ex. 2, p. 27.*