Issues

 Back to main page
ISSUES          
           
Area CCPM EVMS Description Team Resolution
Time buffers hold at appropriate level to protect critical chain each task could hold schedule reserve at lowest level What is appropriate placement of schedule reserve?    
Cost buffers ? management reserve held at total program level Should budget reserves be established for time buffers? What should the value be?    
Buffers     Do buffers have a single WBS or OBS element? What are the alternatives for reporting consumption of buffers? How do we report BCWP against a buffer?    
Schedule probabilities schedule tasks at 50% probability ? What is the normal practice for schedules used to support EVMS? 90% as some suggest?    
Integrated Baseline Reviews   review of schedule, budget realism IBRs typically only look at resources directly supporting the contract. Should we look at company level resources that could be a constraint and therefore a risk?    
BCWS   Currently use early finish for BCWS Use late start? What should we use for BCWS? Does this drive trying to earn budget (BCWP) earlier to state more progress?    
Metrics/Reporting focus on global (project completion) focus on local optima (task completion) Does focusing on optimizing tasks put the entire project in jeopardy? Is this a valid concern?    
Metrics/Reporting     Current EVMS policy of addressing variance thresholds for each task would multiply the number of variance explanations required for CCPM, given 50% probability    
Metrics/Reporting collection of "critical few" metrics "collection of many trivial" metrics What is the correct emphasis for metrics? Do different stakeholders require different metrics?    
Metrics/Reporting % of buffer consumed Cost and schedule variances  What is appropriate early warning that problems are developing?    
Government policy   ANSI/EIA-748-1998 Is there any conflict between the ANSI standard (I.e., 32 criteria) for EVMS and CCPM?    
Time Durations estimated time for task is variable discrete times for each task What do we baseline to?    
Customers     How should we change the focus of our customers to accept CCPM?    

Last Updated on 2/22/00
By Eleanor Haupt
Email: eleanor.haupt@wpafb.af.mil